Mep Work Progress Report Sample [ Premium · Overview ]
Major achievements (e.g., "Main LV Panel energized," "AHU installation complete in Zone A"). Critical bottlenecks or delay warnings. ProjectManager 3. Work Progress Matrix (System-Wise/Floor-Wise)
- [Insert issue/concern 1], [insert description of issue/concern and any actions being taken to address it].
- [Insert issue/concern 2], [insert description of issue/concern and any actions being taken to address it].
- Overall progress: 40%
- Completed: AHU installation at Plant Room A (2 of 3); chilled water main laid to Level 6; ductwork installed on Levels 1 and 3.
- In progress: ductwork on Levels 2 and 4 (60%); insulation of duct mains (30%).
- Issues: spiral duct delivery delayed 6 days — impacts Level 2 finish sequence.
9. Cost Status (MEP portion)
- Contract value (MEP): $3,200,000
- Cost to date (earned): $1,472,000 (46%)
- Variations submitted: 1 (material escalation request — $12,500) — under review
- Forecast: on budget if no further material escalation
- Project Name: ABC Office Building Renovation
- Location: 123 Main St, Anytown, USA
- Reporting Period: February 1 - February 28